Fish love Snags and snags create habitat

Re-snagging the Goulburn to increase native fish habitat and improve recreational fishing opportunities between Seymour and Nagambie.

The Goulburn Broken Catchment Management Authority (CMA) is working along the Goulburn River between Seymour and Nagambie in the coming weeks to increase the amount of large woody habitat, or snags, in the Goulburn River, with the aim to increase in the native fish population and diversity in this section of the river.

Funded by the Victorian Government, through revenue from Recreational Fishing Licenses to improve recreational fishing in Victoria and the Goulburn Broken CMA, the snags are being placed in the Goulburn River, downstream of the Hume Freeway Bridge near Seymour. The works that are being carried out will lead to an increase in habitat for native fish in the area and an improvement in catch rates for recreational fishers.

Goulburn Broken CMA River Health Projects Coordinator, Mr Jim Castles explains, “Native fish rely heavily upon instream habitat such as tree roots, logs and branches called ‘snags’. Since European settlement, our streams and rivers have been de-snagged, in the belief this would increase water flow and quality. We now know this is not the case.”

Native fish ecologists from the Murray Darling Basin Authority estimate that fish populations have declined by 90% since European settlement. There have been many threats to native fish including removal of in-stream and riparian habitat and flow modification.

Snags are the inland equivalent of coastal reefs and provide habitat for native fish and other animals such as tortoises and native water rats. Native fish use them to shelter from fast currents and sunlight and take refuge from predation. Native fish also use snags as feeding and spawning sites, and as nursery areas for juvenile fish.

Recent fish surveys within the Murray Darling Basin have found that 80% of Murray Cod are found within 1 metre of a snag. All large bodied freshwater native fish use snags as habitat.

“Re-snagging is a sound management intervention we can use to restore native fish habitat to our waterways, and results so far suggest that native fish populations respond strongly as a result. Re snagging on its own, however, is unlikely to be the sole driver in native fish recovery in the Goulburn River. The key is to better manage our riparian zones by fencing to restrict stock access and protect native vegetation, and revegetating degraded areas so there will be a constant natural supply of snags in the future” says Mr. Castles. See the dozens of unique artificial fish habitat models, fish attractors and fish cover used at fishiding.com, the leader in  science based, proven, fish protection.

The areas to be re-snagged have been identified via in-stream habitat mapping undertaken in 2011 by scientists from the Arthur Rylah Institute (ARI) in the Goulburn River between the Mitchellstown and Hume Freeway Bridges to identify areas that have a low density of snags. The sites where the Goulburn CMA carry out re-snagging are being selected based on priority zones identified by ARI as a result of this mapping, and access to the waterway within these zones.

The fallen trees used for the re-snagging project have been sourced from a number of nearby locations, including the Nagambie Bypass and a public reserve in Seymour. The Goulburn Broken CMA and its contractors work to rigorous guidelines that have been developed in other locations where re-snagging has been carried out over many years.

“The snags will be secured safely and positioned in a way that does not block the river channel to ensure fishing boats can still travel along the river,” explains Mr Castles “The snags will have very little or no net impact on water flow and will enhance native fish habitat, thereby leading to a more robust native fish community, which will result in huge benefits for recreational fishers in our region.”

This project is funded by the Department of Primary Industries Recreational Fishing Licence Grants Scheme, which uses revenue raised from the sale of recreational fishing licences to fund projects that directly improve recreational fishing in Victoria.

Snags on the riverbank prior to placement. Photo: Jim Castles, Goulburn Broken CMA

Restoration of the Flowing Wells Trout Farm for fish passage and habitat improvement

Manistee River, MI – 10 Waters to Watch Update
Manistee River, MI (Great Lakes Basin FHP)

Purpose of the project
The Conservation Resource Alliance will coordinate the replacement of a degraded road crossing with a timber bridge and the complete restoration of the Flowing Wells Trout Farm for fish passage and habitat improvement.  Implementing this project will open up approximately 31 miles of tributary for fish passage and improve approximately 4 miles of instream habitat on the North Branch of the Manistee River.

The stream will no longer be impounded, sand and sediment will be transported naturally, stream temperatures will recover, stream habitat will improve, and wild brook trout will be able to return to a reach that has been segmented by 12 dams and two dredged channels for approximately 40 years. This project will also improve the overall ecological health of the riparian corridor by improving uplands and wetlands adjacent to the instream restoration work.

Project Timeline
Major earth moving and dam removal at the Flowing Well property will be complete by the fall of 2011.  Additional reptile and amphibian monitoring as well as instream and adjacent habitat improvements will be completed during the summer and fall of 2012.  The bridge at Mecum Road is scheduled to be completed by late 2011.

Partners
The Conservation Resource Alliance is spearheading this project and closely working with the following partners:  National Fish and Wildlife Foundation; U.S. Fish and Wildlife Service; Michigan Department of Natural Resources; Michigan Department of Environmental Quality; Kalkaska County Road Commission; Kalkaska County Conservation District; Upper Manistee River Restoration Committee, Trout Unlimited, USDA-Natural Resources Conservation Service; and Huron Pines.

Updates/Changes
At the Flowing Well Property the following items have been completed.

1st. Quarter, 2011
* Established project timeline for 2011 field season.
* Removed an abandoned beaver dam on upper portion of Flowing Well Creek, blocked adjacent dredged channel, diverted flow back into natural channel.
* Received all required permits including NEPA, SHPO, MDNR, MDEQ, SESC, and Natural Rivers.
* Conducted 2 meetings for potential contractors to begin the bidding process.

2nd Quarter, 2011
* Subcontractor conducted the second season of reptile, amphibian, and macroinvertebrate monitoring, a final report is pending.
* Two volunteer workdays were conducted to clear debris from the N. Branch of the Manistee with project partners (USFWS, MDNR, Trout Unlimited)
* Cleared both Flowing Well Creek and the North Branch of the Manistee River of excess woody debris and blockages including 7 large beaver dams.
* Removed the earthen berm and a buried culvert on Flowing Well Creek using CRA staff and a locally hired work crew. Water is now flowing in its natural banks.
* Performed gradual drawdowns by removing boards at dams #3, #7, and #8, all boards have now been removed.

See the dozens of unique artificial fish habitat models, fish attractors and fish cover used at fishiding.com, the industry leader and only science based, man made and artificial fish habitat, proven to provide all fish with cover they prefer to prosper.

At the Mecum Road site the following has been completed.
* Seven project partner meetings were held to discuss project progress (2 on-site, 2 at road commission office, and 3 committee meetings).
* Contracting, bidding, and legal review of documents.
* County, State and Federal permits obtained: SESC, SHPO, NEPA, MDEQ, and MDNR Natural Rivers.
* Property owner outreach and easement – State of Michigan use permit and permission for easement from 1 private parcel on southwest corner of road crossing.
* Survey, hydraulic analysis, soil borings/analysis, and bridge design completed.

Media coverage updates

http://www.michiganrivernews.com/2011/06/river-rehab-projects-put-michigan-in-national-spotlight/